A full home renovation is the biggest project most homeowners take on short of building new. It touches layout, structure, systems and finishes across most of the house, and it usually takes months rather than weeks. This guide explains what a full renovation normally includes, how the time breaks down from first meeting to move-in, and what tends to stretch the schedule in Edmonton. For an overview of how we approach these projects, see full home renovations.
What is included in a full home renovation?
There is no fixed definition, but a full renovation typically covers several of the following at once:
- Layout changes: removing or moving walls to open the main floor, reworking bedrooms, adding an ensuite or walk-in closet. Structural changes need engineering and permits.
- Kitchen and bathrooms: new kitchen and bathrooms, often the largest share of the budget.
- Systems: electrical panel and wiring upgrades, new plumbing, a high-efficiency furnace, ventilation and sometimes air conditioning.
- Building envelope: insulation, windows, doors and air sealing, which make a noticeable difference to comfort through an Edmonton winter.
- Finishes throughout: flooring, trim, doors, lighting, paint and built-ins.
- Often: basement development, a mudroom or laundry room, or a home addition.
How long does a full home renovation take?
The time is split between planning and construction, and planning is often longer than people expect.
1. Consultation, estimate and design
Defining the scope, measuring the house, developing the design and making selections usually takes several weeks, longer if the design involves structural changes or many custom elements. Decisions made here prevent changes during construction, which are the most common cause of delays.
2. Permits
Structural, electrical, plumbing, gas and mechanical work all need permits in Edmonton. Review times vary with the City’s workload and the complexity of the drawings. Our article on renovation permits in Edmonton explains the types.
3. Ordering
Custom cabinetry, windows, counters, specialty tile and some fixtures have lead times of several weeks or more. They are ordered during design and permitting so they arrive when needed.
4. Construction
Demolition, structural work, rough-ins, inspections, insulation, drywall and finishing typically take several months for a full renovation, depending on the size of the house and the scope. Inspections happen at set stages and work cannot continue past them until they pass.
5. Completion and walkthrough
Final inspections, deficiencies and a detailed walkthrough close out the project.
What stretches the schedule
- Hidden conditions: outdated wiring, plumbing problems, moisture or previous unpermitted work found after demolition. Older homes are more likely to have surprises; see what no one tells you about home renovations.
- Changes mid-project: new ideas after construction starts can mean re-ordering, re-permitting or redoing work.
- Late selections: decisions not made before construction hold up trades.
- Lead times and inspections: back-ordered materials and inspection scheduling.
- Winter: exterior work, concrete and window replacement are harder in deep cold, so they are scheduled carefully.
Can you live at home during a full renovation?
Sometimes. If the work can be phased so a kitchen or bathroom stays usable, many families stay. When the whole main floor is opened up, the house loses heat or water for periods, or there is significant dust and noise, moving out for part or all of the project is usually easier and can shorten the schedule. Our survival guide to living through a renovation helps you decide.
Renovate or rebuild?
When the scope approaches a full gut of the house, it is worth comparing a renovation with a rebuild or infill. The condition of the foundation and structure usually decides it.
Frequently asked questions
How long does a full home renovation take in Edmonton?
From first meeting to move-in, many full renovations take several months to a year, with construction itself typically several months. Size, structural work, permits and lead times make the biggest difference.
What is the difference between a full home renovation and a remodel?
The terms overlap. “Full home renovation” usually means work across most of the house, including systems and layout, while a remodel can refer to a single room.
Should I renovate in stages instead?
Staging spreads cost over time but usually costs more overall, because trades return several times and finished areas may need protecting or redoing. Planning the whole house first and then staging the work in a logical order is a good compromise.